Dream House in Maui
Building the Maui House
The Building of the Maui House
by Eric Newman

We contracted with 3D Builders and Design in Maui to build the house in late February, 2008.  3D Builders had a good reputation and was familiar with building challenging designs, remote locations, and high-end homes.  They are not known for being inexpensive or fast.  The president of 3D Builders, Don Roth, lives in the same sub-development on the next street.  Don has an excellent knowledge of construction in Maui and a strong background in framing.  We found Don to be an excellent communicator and had an uncanny ability to quickly understand exactly what we wanted and offered creative suggestions to improve on it.

The house design was single story, three bedroom, three bath, and rather sprawling, with a horizontal projection of the roof area equal to 5,580 sq. ft.  Construction began in March, 2008 on a 12-month contract, and we were blessed with great weather and minimal delays from suppliers.  Framing proceeded quickly, and by September, 2008 the house was wrapped, the windows and some doors were in, and the roof was sheathed with plywood.

I rented a room in the house next door and was on the job site for about 60 percent of the building process.  I would recommend to anybody not to be a pest, but be available as much as possible while construction is taking place — Especially during the critical finishing period.

Worked slowed during the finish work and the final building inspection was November 3, 2009, and we got the keys two days later.  The house was eight months late with a lengthy list of punch list (incomplete) items.

We were pleased with the way the house turned out with very few exceptions.  The flooring was supposed to be engineered acacia flooring, which looks very similar to Hawaiian Koa.  Unfortunately, the engineered acacia flooring arrived in the incorrect color and only solid acacia flooring was available in the correct color.  We felt that engineered flooring would be more stable over humidity and temperature variations, but we were assured that solid flooring would be fine.

The solid acacia flooring was installed in April 2009, and looked beautiful.  The flooring was immediately covered with Masonite to protect it from the balance of the construction process.  In early September 2009, the Masonite removed and the flooring had severe problems.

All the flooring was severely warped and cupped upwards.  Apparently the flooring was installed over plywood that wasn't sufficiently dry, and the moisture caused the bottom of the flooring to expand.  There were also about 50 cracks in the flooring and something was oozing up from the wood.  Lastly, there were over 50 dings and dents.  Some were caused from grit under the Masonite, which was ground into the flooring over time.  Some were just due to carelessness of workers moving ladders and scaffolding which left marks into the wood, and dragging items such as the water heater which left deep gouges.  Most workers seemed to be careful, others clearly were not.

Acacia Hardwood Flooring Ooze
Acacia Hardwood Flooring Ooze

We wanted the flooring replaced, but we got a credit to have the flooring sanded and refinished.  At th time of this writing, we are waiting to schedule the refinishing, and waiting for assurances that everything including the baseboards will not be damaged in the process.

In Hawaii there are several parties and celebrations at different milestones, and we did them all.  The first is a Hawaiian Blessing for the groundbreaking.  Rev. Adam Gomes conducted the blessing and we had an excellent time and thought he did a great job.  Next is the Topping Off party that is usually done when the roof is sheeted, windows are installed, the exterior plywood is up, but the drywall is not yet installed.  The Topping Off party is basically a celebration and thank you lunch for the excavators, concrete crew, framers and other workers.  In some cultures they tie an evergreen branch to the roof.  The final celebration is the house blessing and it is conducted when the house is complete and you are moving in.  You invite everybody to the blessing — Friends, family, workers, contractors, vendors, and neighbors.  Most of our family flew in from the mainland.  Rev. Adam Gomes officiated again, and neighbor and four-time Grammy award winner George Kahumoku, Jr. performed Hawaiian slack key guitar.  The house blessing was the most special and enjoyable of the three events.

Below you'll see tons of pictures and videos of the construction and the three parties, so please take a look.


House from a Helicopter Viewed Overhead.  May 11, 2009
House from a Helicopter Viewed Overhead.  May 11, 2009

=
Framing with a View.  June, 2008

House Design Front Elevation
House Design Front Elevation
Monier Sea Green Saxony Shake Tile Roof Selected

House Floor Plan
House Floor Plan

Current House Floor Plan
Current House Floor Plan
Larger Image

House Site Plan
House Site Plan


Click Thumbnail for Larger Image
Early Grading in March, 2008
Early Grading Started
in March, 2008
More Grading in Late March, 2008
More Grading in
Late March, 2008
Hawaiian Land Blessing / Groundbreaking on April 3, 2008
Hawaiian Land Blessing /
Groundbreaking April 3, 2008
Rev. Adam Gomes with friends at Hawaiian Blessing on April 3, 2008
Rev. Adam Gomes with
friends at Hawaiian Blessing

Hawaiian Blessing on April 3, 2008
Hawaiian Land Blessing /
Groundbreaking April 3, 2008
More Grading in Early April, 2008
More Grading in
Early April, 2008
More Grading in Early April, 2008
More Grading in
Early April, 2008
More Grading in Early April, 2008
More Grading in
Early April, 2008

Foundation Work Early May 2008
Foundation Work
Early May 2008
Foundation Work Early May 2008
Foundation Work
Early May 2008
Foundation Work Early May 2008
Foundation Work
Early May 2008
Foundation Work Early May 2008
Foundation Work
Early May 2008

Foundation Work circa May 10, 2008
Foundation Work
May 10, 2008
Foundation Work Late May, 2008
Foundation Work
Late May, 2008
3D Builders Slowest in Maui
3D Builders
and Design
Garage Retaining Wall Footing in Late May 2008
Garage Retaining
Wall Footing

Guest Bedroom Footing in Late May 2008
Guest Bedroom Footing
Late May 2008
Dining Room Footings in Late May 2008
Dining Room Footings
Late May 2008
Path Down to Lower Clearing in Late May 2008
Path Down to Lower
Clearing, May 2008
Early Morning on Building Site, June, 2008
Early Morning on Building
Site, June, 2008

Framing with a View, June, 2008
Framing with a View
June, 2008
Framing with a View, June, 2008
Framing with a View
June, 2008
Framing with a View, June, 2008
Framing with a View
June, 2008
Garage Retaining Wall in Progress
Garage Retaining Wall
in Progress

Framing House in June, 2008
Framing House
in June, 2008
View from Lower Clearing, June, 2008
View from Lower Clearing
June, 2008
Site of Future Costco Plastic Shed
Site of Future
Costco Plastic Shed
House Decking Early July 2008
House Decking
Early July 2008

House Decking a Few Days Later
House Decking a
Few Days Later
Completed Costco Plastic Shed
Completed Costco
Plastic Shed
Completed Garage Retaining Wall and Trench for Electricity
Completed Garage Retaining
Wall and Trench for Electricity
Lower Clearing with Shed, July 2008
Lower Clearing
with Shed

Post and Pier Framing of Master Bedroom
Post and Pier Framing
of Master Bedroom
4WD ATV in Costco Shed
4WD ATV in
Costco Shed
Delivery of 14 Tons of Blue Rock for Planters and Walls
Delivery of 14 Tons
of Blue Rock
First of Four Blue Rock Planters
First of Four
Blue Rock Planters

First Blue Rock Planter
First Blue
Rock Planter
Graded for Second Costco Shed
Graded for Second
Costco Shed
Roof Truss Delivery in August, 2008
Roof Truss Delivery
in August, 2008
Lower Clearing with Sheds and Planters
Lower Clearing with
Sheds and Planters

Lower Clearing with Sheds and Planters
Lower Clearing with
Sheds and Planters
Two of Four Blue Rock Planters
Two of Four Blue
Rock Planters
Sheds and Rental Car in Lower Clearing in August, 2008
Sheds and Rental Car
in Lower Clearing
New Riding Lawnmower in Second Shed
New Riding Lawnmower
in Second Shed

House Construction Seen From Lower Clearing in August, 2008
House Construction Seen
from Lower Clearing
Roof Trusses Almost All Installed in August, 2008
Roof Trusses Almost All
Installed in August, 2008
Framing in Great Room Dining Area in August, 2008
Framing in Great Room
Dining Area
Framing in Framing in Master Bedroom in August, 2008
Framing in Master Bedroom
and Master Bathroom

Framing in Great Room in August, 2008
Framing in Great Room
in August, 2008
Framing in Office and Guest Room in August, 2008
Framing in Office
and Guest Room
House Construction Seen From from Boy Scout Camp in August, 2008
House Construction Seen
from Boy Scout Camp
Blue Rock Culvert Under Construction
Blue Rock Culvert
Under Construction

Great Room Framing and Roofing, August 31, 2008
Great Room Framing
August 31, 2008
House Viewed From Street August 31, 2008
House Viewed From Street
August 31, 2008
Roof Almost All Sheeted.  Garage and Entry Slabs Poured.  September 4, 2008
Roof Almost All Sheeted
Garage and Entry Slabs Poured
Great Room Framing Looking into Office, September 1, 2008
Great Room Framing
Looking into Office

Office Roof Framing September 1, 2008
Office Roof Framing
September 1, 2008
Office and Hallway Roof Framing September 1, 2008
Office and Hallway
Roof Framing
Guest Room Roof Framing September 1, 2008
Guest Room
Roof Framing
Main Lanai Framing, September 1, 2008
Main Lanai Framing
September 1, 2008

Pumping Concrete, September 3, 2008
Pumping Concrete
September 3, 2008
Pumping Concrete, September 3, 2008
Pumping Concrete
September 3, 2008
Pumping Concrete in Garage, September 3, 2008
Pumping Concrete in Garage
September 3, 2008
Finished Concrete in Garage and Breezeway, September 3, 2008
Finished Concrete in
Garage and Breezeway

Finished Concrete in Formal Entry, September 3, 2008
Finished Concrete
in Formal Entry
Breezeway Framing Started, September 4, 2008
Breezeway Framing Started
September 4, 2008
House Construction Viewed From Entrance, September 4, 2008
House Construction
Viewed From Entrance
House Viewed from Street, Garage Framed, September 21, 2008
House from Street
Garage Framed

Formal Entrance to House
Formal Entrance
to House
House Construction Viewed from Entrance, September 20, 2008
House Construction
Viewed from Entrance
House Construction Viewed from Below, September 22, 2008
House Construction
Viewed from Below
Guest Room and Garage
Guest Room
and Garage

Inside of Garage and Breezeway
Inside of Garage
and Breezeway
Inside of Garage
Inside of
Garage
Inside of Garage and Roof Joists
Inside of Garage
and Roof Joists
Office Framing, September 24, 2008
Office Framing
September 24, 2008

Guest and Office Bathroom Windows, September 24, 2008
Guest and Office
Bathroom Windows
Great Room Looking Toward Dining Room, September 24, 2008
Great Room Looking
Toward Dining Room
Great Room Looking Toward Kitchen, September 24, 2008
Great Room Looking
Toward Kitchen
Framing of 12 ft. x 10 ft. Master Closet, September 24, 2008
Framing of 12 ft. x 10 ft.
Master Closet

Master Bathroom Framing, September 24, 2008
Master Bathroom
Framing
Master Bathroom Sink and Two Closets, September 24, 2008
Master Bathroom Sink
and Two Closets
Master Bedroom, Lanai and Sitting Area, September 24, 2008
Master Bedroom, Lanai
and Sitting Area
Framing of Master Bathroom Bathtub Area, September 24, 2008
Master Bathroom
Bathtub Area Framing

Main Lanai on View Side of House
Main Lanai on
View Side of House
Area Below House Grubbed for Terraced Walls
Area Below House Grubbed
for Terraced Walls
Trench for Top Terraced Wall Footing
Trench for Top
Terraced Wall Footing
Topping Off Party held Oct. 24, 2008
Topping Off Party
Oct. 24, 2008

Topping Off Party held Oct. 24, 2008
Topping Off Party
Oct. 24, 2008
Topping Off Party held Oct. 24, 2008
Topping Off Party
Oct. 24, 2008
Topping Off Party held Oct. 24, 2008
Topping Off Party
Oct. 24, 2008
Topping Off Party held Oct. 24, 2008
Topping Off Party
Oct. 24, 2008

Topping Off Party held Oct. 24, 2008
Topping Off Party
Oct. 24, 2008
Rainbow During Topping Off Party held Oct. 24, 2008
Rainbow During
Topping Off Party
House with Board and Batton Siding Installed, Oct. 26, 2008
House with Board and Batton
Siding Installed
House Viewed From Street.  Siding Installed, Batons on Roof.  November 1, 2008
Batons on Roof
November 1, 2008

Great Room Kitchen Looking Toward Kitchen, Nov. 4, 2008
Great Room Kitchen Looking
Toward Kitchen Nov. 4, 2008
Sliding Glass Pocket Doors in Great Room
Sliding Glass Pocket Doors
in Great Room
FrontEntrance into Great Room
Front Entrance
into Great Room
Fire Sprinklers and Electrical
Fire Sprinklers
and Electrical

Nitch Added Above Guest Room Closet
Nitch Added Above
Guest Room Closet
Riki Starting Top Terraced Blue Rock Wall
Riki Starting Top
Terraced Blue Rock Wall
Blue Rocks On Top Terraced Wall
Blue Rocks On Top
Terraced Wall
Stair Cut Out on Top Terraced Wall
Stair Cut Out on
Top Terraced Wall

Front Entrance with Facia Painted
Front Entrance with
Facia Painted
Another View of Front Entrance with Facia Painted
Front Entrance with
Facia Painted
Front Entrance with Ceiling
Front Entrance and
Ceiling
Sliding Glass Pocket Doors with Nitch Above
Sliding Glass Pocket
Doors with Nitch Above

Fireplace Roughed in.  November 6, 2008
Fireplace Roughed in
November 6, 2008
House Viewed From Street.  Chimney Roughed in.  November 6, 2008
Chimney Roughed in
November 6, 2008
House Viewed From Street.  Monier Tile Roof Installed.  January 9, 2009
Monier Tile Roof Installed
January 9, 2009
Fireplace in Great Room.  January 9, 2009
Fireplace in Great Room
January 9, 2009

Main Lanai.  January 9, 2009
Main Lanai
January 9, 2009
First Terraced Blue Rock Wall.  January 9, 2009
First Terraced
Blue Rock Wall
First Terraced Blue Rock Wall and Lanai.  January 18, 2009
First Terraced Blue
Rock Wall and Lanai
First Terraced Blue Rock Wall Stairway Cut Out.  January 24, 2009
First Terraced Blue Rock
Wall Stairway Cut Out

House Viewed from Street Below.  January 10, 2009
House Viewed from
Street Below
House Viewed from Lower Clearing.  January 10, 2009
House Viewed from
Lower Clearing
Driveway Grading around Road Storm Drain Culvert.  January 24, 2009
Driveway Grading around
Road Storm Drain Culvert
Driveway Grading around Road Storm Drain Culvert.  January 24, 2009
Driveway Grading around
Road Storm Drain Culvert

Driveway Grading around Road Storm Drain Culvert.  January 24, 2009
Driveway Grading around
Road Storm Drain Culvert
Lots of Wires in Equipment Closet.  January 24, 2009
Lots of Wires in
Equipment Closet
Soffit in Office / Bedroom #2.  January 24, 2009
Soffit in Office /
Bedroom #2
Air Returns Framed in Office / Bedroom #2.  January 24, 2009
Air Returns Framed in
Office / Bedroom #2

200 Amp Electrical Panels in Garage.  January 24, 2009
200 Amp Electrical
Panels in Garage
Kitchen with Soffits and Island.  January 24, 2009
Kitchen with Soffits
and Island
Top Soil Delivery for Backfilling Blue Rock Walls.  January 26, 2009
Top Soil Delivery for
Backfilling Rock Walls
Top Soil for Backfilling Blue Rock Walls.  January 26, 2009
Top Soil for Backfilling
Blue Rock Walls

Cement Board on Main Lanai.  Feb. 20, 2009
Cement Board on
Main Lanai
Great Room with Insulation.  Feb. 20, 2009
Great Room with
Insulation Installed
Floor Insulation Under House.  Feb. 18, 2009
Floor Insulation
Under House
Great Room with Sheet Rock Installed.  March 1, 2009
Great Room with
Sheet Rock Installed

Great Room with Sheet Rock Installed.  March 1, 2009
Great Room with
Sheet Rock Installed
First Two Blue Rock Terraced Walls.  March 5, 2009
First Two Blue Rock
Terraced Walls
First Two Blue Rock Terraced Walls.  March 5, 2009
First Two Blue Rock
Terraced Walls
Hardwood Flooring Delivered and Acclimatizing in Great Room.  March 7, 2009
Hardwood Flooring Delivered &
Acclimatizing in Great Room

Wood Installed on Soffits under Eaves.  March 7, 2009
Wood Installed on
Soffits under Eaves
Great Room Quadruple Sliding Glass Door in Great Room.  March 7, 2009
Great Room Quadruple
Sliding Glass Door
Windows in Office (Second Bedroom).  March 7, 2009
Windows in Office
(Second Bedroom)
Windows in Master Bedroom.  March 7, 2009
Windows in
Master Bedroom

Private Lanai off Guest Bedroom.  March 7, 2009
Private Lanai off
Guest Bedroom
Exterior Being Painted. March 26, 2009
Exterior of House
Being Painted
Exterior Being Painted. April 6, 2009
Exterior Being Painted
April 6, 2009
Main Lanai and Terraced Walls From Below.  March 26, 2009
Main Lanai and Terraced
Walls From Below

Guest Room and Side of Garage.  March 26, 2009
Guest Room and
Side of Garage
House Viewed from Lower Clearing.  April 7, 2009
House Viewed from
Lower Clearing
Pre Open House Party with Family.  March 29, 2009
Pre Open House
Party with Family
Installation of Cedar Ceiling in Great Room.  April 2, 2009
Installation of Cedar
Ceiling in Great Room

Installation of Cedar Ceiling in Great Room.  April 2, 2009
Installation of Cedar
Ceiling in Great Room
Installation of Cedar Ceiling in Great Room.  April 4, 2009
Installation of Cedar
Ceiling in Great Room
Installation of Cedar Ceiling in Main Lanai.  April 7, 2009
Installation of Cedar
Ceiling on Main Lanai
Forms on 200 ft. Long Driveway to Lower Clearing.  March 26, 2009
Forms on 200 ft. Long
Driveway to Lower Clearing

First of Four Concrete Trucks And Pump.  April 1, 2009
First of Four Concrete
Trucks And Pump
Pouring 200 ft. Long Driveway to Lower Clearing.  April 1, 2009
Pouring 200 ft. Long
Driveway to Lower Clearing
Pouring 200 ft. Long Driveway to Lower Clearing.  April 1, 2009
Pouring 200 ft. Long
Driveway to Lower Clearing
Finishing Offramp to Water Tank.  April 1, 2009
Finishing Offramp to
Water Tank

Long Driveway Formed and No. 10 Mesh.  April 1, 2009
Long Driveway Formed
and No. 10 Mesh
Slowly Working Down Long Driveway.  April 1, 2009
Slowly Working Down
Long Driveway
Slowly Working Down Long Driveway.  April 1, 2009
Slowly Working Down
Long Driveway
Rough Broom Finish on Driveway.  April 1, 2009
Rough Broom Finish
on Driveway

Starting to Pull Forms on Driveway.  April 1, 2009
Starting to Pull
Forms on Driveway
Completed Driveway to Lower Clearing.  April 8, 2009
Completed Driveway
to Lower Clearing
End of Driveway in Lower Clearing.  April 7, 2009
End of Driveway
in Lower Clearing
House and Driveway from Maluhia Entrance.  April 4, 2009
House and Driveway
from Maluhia Entrance

Guest Room Porcelain Tile Installation.  April 7, 2009
Guest Room Porcelain
Tile Installation
Guest Room Porcelain Tile Installation.  April 7, 2009
Guest Room Porcelain
Tile Installation
Guest Room Porcelain Tile Installation.  April 7, 2009
Guest Room Porcelain
Tile Installation
Guest Lanai Porcelain Tile Installation.  April 7, 2009
Guest Lanai Porcelain
Tile Installation

Guest Lanai Porcelain Tile Installation.  April 7, 2009
Guest Lanai Porcelain
Tile Installation
Ricky Building Blue Rock Wall Below Water Tank.  March 26, 2009
Ricky Building Blue Rock
Wall Below Water Tank
House from a Helicopter.  May 11, 2009
House from a Helicopter
May 11, 2009
House from a Helicopter Viewed Overhead.  May 11, 2009
House from a Helicopter
Viewed Overhead

House from a Helicopter Viewed Overhead.  May 11, 2009
House from a Helicopter
Viewed Overhead
Master Bedroom Viewed from Below, April 22, 2009
Master Bedroom Viewed
from Below
Acacia Hardwood Flooring Being Installed in Great Room, April 22, 2009
Acacia Hardwood Flooring
Being Installed in Great Room
Cedar Reflective Ceiling in Great Room, April 22, 2009
Cedar Reflective Ceiling
in Great Room

Cedar Reflective Ceiling in Front Lanai Entrance, April 22, 2009
Cedar Reflective Ceiling
in Front Lanai Entrance
Cedar Reflective Ceiling in Main Lanai, May 6, 2009
Cedar Reflective Ceiling
in Main Lanai
House Viewed from Maluhia Entrance, April 27, 2009
House Viewed from
Maluhia Entrance
French Doors in Breezeway, April 27, 2009
French Doors in
Breezeway

Garage, Breezeway, and Front Entrance, April 27, 2009
Garage, Breezeway,
and Front Entrance
Acacia Flooring Being Installed in Office, April 29, 2009
Acacia Flooring Being
Installed in Office
Load of EKO Systems Compost, May 2, 2009
Load of EKO Systems
Compost
Driveway Retaining Wall Footing, May 4, 2009
Driveway Retaining
Wall Footing

Driveway To Lower Clearing and Retaining Wall, May 6, 2009
Driveway To Lower Clearing
and Retaining Wall
World's Steepest Driveway at 24 Degrees (44.5 %), May 6, 2009
World's Steepest Driveway
at 24 Degrees (44.5 %)
World's Steepest Driveway at 24 Degrees, May 6, 2009
World's Steepest Driveway
at 24 Degrees
Terraced Walls Being Backfilled, May 6, 2009
Terraced Walls
Being Backfilled

Steeper than the World's Steepest Driveway (only 22 degrees or 40%)

First Two Terraced Walls Backfilled, May 6, 2009
First Two Terraced
Walls Backfilled
Dining Room Pond Being Dug, May 7, 2009
Dining Room Pond
Being Dug
Interior Finish Load Delivery, May 8, 2009
Interior Finish
Load Delivery
Ponds Dug, Front being Graded. May 13, 2009
Ponds Dug
Front being Graded

Master Bathroom Cabinets Installed. May 15, 2009
Master Bathroom
Cabinets Installed
Great Room with Kitchen Cabinets being Installed. May 15, 2009
Great Room with Kitchen
Cabinets being Installed
Kitchen Island Cabinets being Installed. May 18, 2009
Kitchen Island
Cabinets Installed
Kitchen Cabinets being Installed. May 18, 2009
Kitchen Cabinets
being Installed

Kitchen Cabinets being Installed. May 18, 2009
Kitchen Cabinets
being Installed
Kitchen Cabinets being Installed. May 18, 2009
Kitchen Cabinets
being Installed
Office Bathroom Cabinets being Installed. May 15, 2009
Office Bathroom Cabinets
being Installed
Footing for Third Terraced Wall. May 16, 2009
Footing for
Third Terraced Wall

Driveway with Blue Rock Retaining Wall. May 19, 2009
Driveway with Blue
Rock Retaining Wall
Tank Offramp on Driveway to Lower Clearing. May 19, 2009
Tank Offramp on Driveway
to Lower Clearing
Third Terraced Wall Complete.  June 2, 2009
Third Terraced
Wall Complete
Slate Veneer on Lanai Column.  June 2, 2009
Slate Veneer
on Lanai Column

Slate Veneer on Front Columns.  June 2, 2009
Slate Veneer
on Front Columns
Louvered Doors Installed in Hallway.  June 2, 2009
Louvered Doors
Installed in Hallway
First Crop of Tomatoes.  June 3, 2009
First Crop of
Tomatoes
Front Doors Installed.  June 5, 2009
Front Doors
Installed

Wainscoting Installed in Office.  June 10, 2009
Wainscoting Installed
in Office
Trench for Six Inch Gutter Pipe to Catchment Water Tank.  June 11, 2009
Trench for Six Inch Gutter
Pipe to Catchment Water Tank
Six Inch Gutter Pipe with Valve and Overflow.  June 11, 2009
Six Inch Gutter Pipe with
Valve and Overflow
Wainscoting Installed in Breezeway. June 12, 2009
Wainscoting Installed
in Breezeway

Stained Cedar Ceiling on Lanai. June 12, 2009
Stained Cedar Ceiling
on Lanai
Copper Gutters Formed On Site. June 12, 2009
Copper Gutters
Formed On Site
First Length of Copper Gutters Installed. June 14, 2009
First Length of
Copper Gutters Installed
House Viewed From Street.  Copper Gutters and Slate being Installed.  June 15, 2009
Copper Gutters and
Slate being Installed

Great Room Beam Wrapped in Hardwood. June 15, 2009
Great Room Beam
Wrapped in Hardwood
Great Room with Kitchen and Cedar Ceiling. June 15, 2009
Great Room with Kitchen
and Cedar Ceiling
Great Room with Kitchen and Cedar Ceiling. June 15, 2009
Dining Room
in Great Room
Solid Copper Gutters on Roof. June 16, 2009
Solid Copper Gutters
on Roof

Bamboo Being Installed on Master Bedroom Ceiling. June 17, 2009
Bamboo Being Installed
on Master Bedroom Ceiling
Ground Breaking on Barn/Workshop 6/24/09
Ground Breaking on
Barn/Workshop 6/24/09
 Jacaranda Tree in Lower Clearing. July 25, 2009
Jacaranda Tree
in Lower Clearing
Rainforest Green Granite Installed in Office Shower. July 25, 2009
Rainforest Green Granite
Installed in Office Shower

Glass Tiles Installed Around Future Mirror in Office Shower. July 25, 2009
Glass Tiles Installed Around
Future Mirror in Office Shower
Great Room Ceiling Fans Installed. July 25, 2009
Great Room Ceiling
Fans Installed
Dining Room Behind Fireplace. July 25, 2009
Dining Room
Behind Fireplace
Great Room Looking Toward Kitchen. July 25, 2009
Great Room Looking
Toward Kitchen

Shower in Master Bathroom. July 25, 2009
Shower in
Master Bathroom
Ceiling Fan in Master Bathroom. July 25, 2009
Ceiling Fan in
Master Bathroom
Sixth and Final Terraced Wall Complete. July 25, 2009
Sixth and Final
Terraced Wall Complete
Bananas in Lower Clearing. July 27, 2009
Bananas in Lower Clearing
July 27, 2009

First Bananas in Lower Clearing. July 27, 2009
First Bananas
July 27, 2009
Six Terraced Walls Viewed from Below. July 27, 2009
Six Terraced Walls
Viewed from Below
Front Walkways Being Formed, August 19, 2009
Front Walkways
Being Formed
Guest Room Kitchen Backsplash, August 19, 2009
Guest Room
Kitchen Backsplash

Guest Room Bathroom Sink, August 19, 2009
Guest Room
Bathroom Sink
Guest Room Bathroom Shower, August 19, 2009
Guest Room
Bathroom Shower
Kitchen in Great Room, August 19, 2009
Kitchen in
Great Room
Kitchen Island and Backsplash, August 19, 2009
Kitchen Island
and Backsplash

Solid Monkeypod Desk in Office, Sept. 1, 2009
Solid Monkeypod
Desk in Office
Epoxy Coating on Garage Floor, Sept. 1, 2009
Epoxy Coating on
Garage Floor
Ricky Working on North End of Third Terraced Wall, Sept. 1, 2009
Ricky Working on North
End of Third Terraced Wall
Pebble Shower Pan in Office, Sept. 1, 2009
Pebble Shower Pan
in Office

Bananas Continuing to Grow, Sept. 2, 2009
Bananas Continuing
to Grow
Master Bathroom Under Construction, Sept. 2, 2009
Master Bathroom
Under Construction
Master Bathroom Floor Tile, Sept. 2, 2009
Master Bathroom
Floor Tile
Twins Craig and Dean Working on Lanai Railing, Sept. 2, 2009
Twins Craig and Dean
Working on Lanai Railing

Solid Monkeypod Desk in Office, Sept. 5, 2009
Solid Monkeypod Desk
in Office
Glass Vessel Sink in Office Bathroom, Sept. 7, 2009
Glass Vessel Sink
in Office Bathroom
Glass Artist Tom Trottier and the Sandblasted Front Doors, Sept. 16, 2009
Glass Artist Tom Trottier and
the Sandblasted Front Doors
Sandblasted Front Doors at Night, Sept. 16, 2009
Sandblasted Front Doors
at Night

Sandblasted Front Doors from Outside, Sept. 29, 2009
Front Doors
from Outside
Sandblasted Main Hallway Door, Sept. 25, 2009
Sandblasted
Main Hallway Door
Satellite Dishes Below Master Bedroom, Sept. 25, 2009
Satellite Dishes Below
Master Bedroom
Main Entry and Inlaid Humpback Whales, Sept. 29, 2009
Main Entry and
Inlaid Humpback Whales

Great Room and Kitchen, Sept. 30, 2009
Great Room
and Kitchen
Master Bath Tub and Shower, Sept. 30, 2009
Master Bath Tub
and Shower
Great Room with TV and Fireplace, Sept. 30, 2009
Great Room with
TV and Fireplace
Main Lanai Viewed from Great Room, Sept. 30, 2009
Main Lanai Viewed
from Great Room

Great Room and Kitchen, Oct. 1, 2009
Great Room
and Kitchen
Great Room with TV and Fireplace, Oct. 1, 2009
Great Room with
TV and Fireplace
Turtle Inlay in Breezeway, Oct. 7, 2009
Turtle Inlay
in Breezeway
Master Bathroom Sinks and Avi Kiriaty Artwork, Oct. 10, 2009
Master Bathroom Sinks
and Avi Kiriaty Artwork

Guest Room LCD Flat Screen HD TV, Oct. 12, 2009
Guest Room LCD
Flat Screen HD TV
Great Room LED Flat Screen HD TV and Speakers, Oct. 15, 2009
Great Room LED Flat Screen
HD TV and Speakers
Last of Driveway Poured, Oct. 15, 2009
Last of Driveway
Poured
Terraced Walls Viewed from Below, Oct. 23, 2009
Terraced Walls
Viewed from Below

Stairs Off Guest Lanai, Oct. 23, 2009
Stairs Off
Guest Lanai
Blue Rock Wall in Front, Oct. 23, 2009
Blue Rock Wall
in Front
House Viewed From Street, Oct. 23, 2009
House Viewed From Street
October 23, 2009
Painted Stainless Steel Metal Art on Front of House, Oct. 26, 2009
Painted Stainless Steel Metal
Art on Front of House

Great Room Torn Up Again for Ceiling Repair, Oct. 28, 2009
Great Room Torn Up Again
for Ceiling Repair
Plantains Ready to Pick, Oct. 28, 2009
First Plantains Ready
to Pick
Repainting Master Bedroom, Oct. 29, 2009
Repainting
Master Bedroom
Columns Under House Getting Textured, Oct. 29, 2009
Columns Under House
Getting Textured

Retaining Wall Getting Textured, Oct. 29, 2009
Retaining Wall
Getting Textured
Blue Rock Walls in Front of House, Oct. 29, 2009
Blue Rock Walls
in Front of House
Wood Storage for Wood Fired Pizza Oven, Oct. 29, 2009
Wood Storage for Wood
Fired Pizza Oven
Blue Rock Walls and Fire Pit, Oct. 29, 2009
Blue Rock Walls
and Fire Pit

Fire Pit in Front Under Construction, Oct. 29, 2009
Fire Pit in Front
Under Construction
Blue Rock Stairs in Front Under Construction, Oct. 29, 2009
Blue Rock Stairs in
Front Under Construction
Blue Rock Fire Pit Almost Done, Oct. 30, 2009
Blue Rock Fire Pit
Almost Done
Blue Rock Fire Pit Done, Oct. 31, 2009
Blue Rock Fire
Pit Done

Front Blue Rock Walls Almost Done, Oct. 31, 2009
Front Blue Rock Walls
Almost Done
Master Bathroom Being Painted, Nov. 5, 2009
Master Bathroom
Being Painted
Front Walkways Acid Stained and Sealed, Nov. 5, 2009
Front Walkways Acid
Stained and Sealed
Front Walkways Acid Stained and Sealed, Nov. 5, 2009
Front Walkways Acid
Stained and Sealed

Side Walkways Acid Stained and Sealed, Nov. 5, 2009
Side Walkways Acid
Stained and Sealed
Ricky's Long Wall from Driveway to Barn, Dec. 9, 2009
Ricky's Long Wall
from Driveway to Barn
House Viewed From Street, January 5, 2010
House Viewed From Street
January 5, 2010
Tea Room by Edward Gordon on Fireplace in Dining Room, January 12, 2010
Tea Room by Edward Gordon
on Fireplace in Dining Room

Terraced Walls with Stairs Viewed from Below, January 13, 2010
Terraced Walls with Stairs
Viewed from Below
Office Bathroom Painted, January 13, 2010
Office Bathroom Painted
January 13, 2010
Master Bedroom Painted January 17, 2010
Master Bedroom Painted
January 17, 2010
Master Bathroom Painted, January 13, 2010
Master Bathroom Painted
January 17, 2010

Master Bathroom Painted, January 13, 2010
Master Bathroom Painted
January 17, 2010
Landscaping in front of Guest Room, February 6, 2010
Landscaping in front
of Guest Room
Landscaping along Driveway, February 6, 2010
Landscaping along Driveway
February 6, 2010
LED Solar Landscaping Lights at Dusk, February 8, 2010
LED Solar Landscaping
Lights at Dusk

House Blessing, March 20, 2010
House Blessing
March 20, 2010
House Blessing, March 20, 2010
House Blessing
March 20, 2010
House Blessing, March 20, 2010
House Blessing
March 20, 2010
House Blessing, March 20, 2010
House Blessing
March 20, 2010

House Blessing, March 20, 2010
House Blessing
March 20, 2010
Master Bedroom Drapes and a Full Moon over Haleakala, April 29, 2010
Master Bedroom Drapes and
Full Moon over Haleakala
Top Pond Dug, April 30, 2010
Top Pond Dug
April 30, 2010
Top Pond, Bridge, and Stream, April 30, 2010
Top Pond, Bridge,
and Stream

Top Stream and Bottom Pond Dug, April 30, 2010
Stream and
Bottom Pond Dug
Bottom Pond Dug, April 30, 2010
Bottom Pond Dug
April 30, 2010
Biofilter Dug, April 30, 2010
Biofilter Dug
April 30, 2010
Biofilter and Top Pond, April 30, 2010
Biofilter and
Top Pond

House Viewed From Street, May 10, 2010
House Viewed From Street
May 10, 2010
House and Barn at Night, May 11, 2010
House and Barn at Night
May 11, 2010
Koa Trees on Slope Above House, August 12, 2010
Koa Trees on Slope
Above House
Neighbor George Kahumoku Jr. Helping Harvest Taro, August 20, 2010
Neighbor George Kahumoku Jr.
Helping Harvest Taro

Outdoor Wood-Fired Pizza Oven, September 11, 2010
Outdoor Wood-Fired
Pizza Oven
Blue Rock Veneer on Pizza Oven, September 13, 2010
Blue Rock Veneer
on Pizza Oven
Blue Rock Veneer on Pizza Oven Chimney, September 14, 2010
Blue Rock Veneer on
Pizza Oven Chimney
Completed Outdoor Pizza Oven, September 18, 2010
Completed Outdoor
Pizza Oven

Walls and Path above Pizza Oven, October 9, 2010
Walls and Path
above Pizza Oven
House Viewed From Street, October 9, 2010
House Viewed From Street
October 9, 2010
Clouds Reflecting of Water, November 3, 2010
Clouds Reflecting of Water
November 3, 2010
 Nine Monkeypod Trees Planted Along Path to Barn, November 9, 2010
Nine Monkeypod Trees
Planted Along Path to Barn

First Fire in Outdoor Pizza Oven, November 9, 2010
First Fire in
Outdoor Pizza Oven
Hawaiian Girl Oil Painting, November 10, 2010
Hawaiian Girl
Oil Painting
Lawai Fern along Driveway, November 15, 2010
Lawai Fern Planted
along Driveway
Lawai Fern along Driveway, November 15, 2010
Lawai Fern Planted
along Driveway

Lawai Fern along Driveway, November 15, 2010
Lawai Fern Planted
along Driveway
Taro on Top Terrace, January 16, 2011
Taro Growing on
Top Rock Terrace
Master Bedroom with Jai Lu Painting and Bed, August 3, 2012
Master Bedroom
with Jai Lu Painting
Master Viewed from Bedroom, August 8, 2012
Master Bathroom
Viewed from Bedroom

Master Bathroom Panorama, August 8, 2012
Master Bathroom
Panorama
Master Bathroom Panorama, August 8, 2012
Master Bathroom
Panorama
Four Erics in Front of House Panorama, August 25, 2012
Four Erics in Front
of House Panorama
Dusk From Main Lanai Panorama, August 26, 2012
Dusk From Main
Lanai Panorama

Moonlight Through Heavy Clouds, August 29, 2012
Moonlight Through Clouds
Moonrise Panorama, August 31, 2012
Moonrise Panorama
Moonrise Through Clouds, September 2, 2012
Moonrise Through Clouds
Sunrise From Main Lanai Panorama, October 25, 2012
Sunrise From Main Lanai

Click Thumbnail for Larger Image

Panoramic View of House and Barn. February, 2011
Panoramic View of House and Barn.  February, 2011

Panoramic View of House and Barn. February, 2011
Panoramic View of House and Barn.  September, 2012

Click Thumbnail to Watch Video
Need a DivX Player?

Video of Second ATV Ride
ATV Ride 2
Video of Gate Layout
Gate Layout
Video of Overview of Grading Progress (Apr. 2008)
Grading Progress (Apr. 2008)
Detail of Grading Progress (Apr. 2008)
Grading Progress 2 (Apr. 2008)

Foundation Late May, 2008
Foundation Late May, 2008
Walking Around Foundation, Late May, 2008
Walking Around Foundation
Foundation from Top of Piers in Late May, 2008
Foundation from Top of Piers
Driveway from Lower Clearing in Late May 2008
Driveway from Lower Clearing

Location of First Water Tank
Location of First Water Tank
Canoe On Property
Canoe On Property
Video of Lower Clearing June 2008
Lower Clearing June 2008
Video of Garage Retaining Wall June 2008
Garage Retaining Wall

Video of Building Site in June 2008
Building Site in June 2008
Video of Building Site in June 2008
Building Site in June 2008
Video of Building Site in July 2008
Building Site in July 2008
Video of Framing Status July 2008
Framing Status July 2008

Video of Electrical Trench, July 2008
Electrical Trench July 2008
Video of Third ATV Ride
ATV Ride 3
Video of Work in Lower Clearing, July 2008
Video of Work in Lower Clearing
Video of Framing Status on View Side of House, August 2008
View Side of House

Video of Framing Status August 2008
Framing Status August 2008
Video of Roof Framing Up, August 2008
Roof Framing Up
Video of Posts and Piers Under House, August 2008
Posts Under House
Video of House Walk Through, Sept. 1, 2008
Sept. 1 House Walk Through

Video of House From Street, September 2008
House From Street
Pouring Garage Slab, September 2008
Pouring Garage Slab
Pouring Garage Slab, September 2008
Pouring Garage Slab
Video of House From Street, September 4, 2008
House From Street

Video of House Walk Through, Sept. 19, 2008
Sept. 19 House Walk Through
Video of Lower Lot Septic Tank, Leech Field, and Misc. Work, Sept. 19, 2008
Septic and Lower Lot Work
Video of Septic Tank and Leech Field, Sept. 19, 2008
Septic Tank and Leech Field
Video of House From Street, Sept. 19, 2008
House From Street

Video of Grubbing for Blue Rock Terraced Walls, Sept. 24, 2008
Grubbing for Blue Rock Walls
Video of House Walk Through, Sept. 24, 2008
Sept. 24 House Walk Through
Video of HouseWalkThrough, Nov. 4, 2008
House Walk Through
Video of House From Street, Nov. 6, 2008
House From Street

Time Lapse Video, Jan. 18, 2009
Time Lapse Video
House Walk Through, Jan. 18, 2009
House Walk Through
Video of Area Above House, Jan. 24, 2009
Area Above House
Video of Grading Around Driveway, Jan. 24, 2009
Grading Around Driveway

Video of Grading Around Driveway, Jan. 24, 2009
Grading Around Driveway
Video of Fourth ATV Ride, Jan. 25, 2009
ATV Ride 4
Video of Workshop Staking.  Viewed from front driveway, Feb. 20, 2009
Workshop Staking
Video of Workshop Staking.  Viewed from front, Feb. 20, 2009
Workshop Staking from Front

Video of Workshop Staking.  Viewed from above, Feb. 20, 2009
Workshop Staking from Above
Video of Workshop Staking.  Viewed from back, Feb. 20, 2009
Workshop Staking from Back
Video of House Walk Through with Drywall Up, Feb. 25, 2009
House with Drywall Up
Wide Angle Walkthrough while Mudding, Mar. 6, 2009
Wide Angle Walkthrough

Video of Second Blue Rock Wall.  March 5, 2009
Second Blue Rock Wall
Video of Second Blue Rock Wall with Wide Angle Lens.  March 6, 2009
Second Wall Wide Angle
Looking Around from Driveway to Lower Clearing.  Feb. 26, 2009
Looking Around from Driveway
Outside Painted and Interior Primered.  March 26, 2009
Outside Painted Inside Primered

Pouring Driveway to Lower Clearing.  April 1, 2009
Pouring Lower Driveway
Pouring Driveway to Lower Clearing.  April 1, 2009
Pouring Lower Driveway
Pouring Driveway to Lower Clearing.  April 1, 2009
Pouring Lower Driveway
Pouring Driveway to Lower Clearing.  April 1, 2009
Pouring Lower Driveway

Long Driveway to Lower Clearing.  April 4, 2009
Long Lower Driveway
Layout of Ponds in Front Yard.  May 4, 2009
Layout of Ponds in Front
Footing for Driveway Retaining Wall.  May 4, 2009
Footing for Retaining Wall
First Two Blue Rock Walls Backfilled.  May 6, 2009
Blue Rock Walls Backfilled

Video of House From Street, May 19, 2009
House From Street
Third Blue Rock Wall.  June 2, 2009
Third Blue Rock Wall
House Viewed from Road Showing Copper Gutter Installation.  June 15, 2009
Copper Gutter Installation
Copper Gutter Installation.  June 15, 2009
Copper Gutter Installation

House Walkthrough.  June 15, 2009
House Walkthrough 6/15/09
House Walkthrough.  July 3, 2009
House Walkthrough 7/3/09
House Walkthrough.  July 12, 2009
House Walkthrough 7/12/09
House Walkthrough.  July 25, 2009
House Walkthrough 7/25/09

All Six Terraced Walls From Below.  July 27, 2009
Six Terraced Walls From Below
House Walkthrough.  August 9, 2009
House Walkthrough 8/9/09
House Walkthrough.  August 19, 2009
House Walkthrough 8/19/09
House Blessing.  March 20, 2010
House Blessing 3/20/10

ATV Ride Around Property.  November 9, 2010
ATV Ride Around Property
Clouds Through the Bedroom Window.  November 10, 2011
Clouds Through the Window
Need a
DivX Player?


Click Thumbnail
to Watch Video




to build a house, a beautiful one,
i just do not need land and nails
not just wood, and grass
not just beams and roofs, for they

are but necessities, projections of
the house upon a hill
of the mind,

to build a house, one needs the soul
of the home,
the words of memories, the gutters
of our emotions,

unlike you, my house requires the fences
and walls
keeping away the ill winds
of publicity, the rumors of who i was,

a slope, the steep one, inclined
towards no other
than the whiteness of the sky

— Ric S. Bastasa



Copyright © 2011 - 2013 Eric Newman * All rights reserved


Introduction

The Bare Lot

The Initial Planning

The House Never Built

The Building of the House

Catchment Water Design

The Farm Plan

Terraced Walls

Outrigger Canoe

Canoe Hut

The Building of the Barn

Things to do on Maui

Notable People

Eric Newman Home
































































World's Best
55-inch
Solid Brass
Harbormaster
Telescope

Stanley London